Qwikinstall.com logo
USA logo

US Patent 9,115,501

Canada Patent 2,846,874


Blog Layout

Construction Trade Damage

Construction Trade Damage

In the book titled Construction Management “Subcontractors Scope of Work”, written by Jason G. Smith and Jimmie Hinze in 2010, they state that costs associated with trade damage to door frames are “inevitable” and must be accounted for in the quoting and planning process.



Here are some excerpts from their research: 


“Construction is a massive and fast-paced operation. Understandably, it must be realized that minor trade damage is part of construction and needs to be accounted for on every project. The framing subcontractor should include an allowance in their bid for repairing the inevitable cases of minor trade damage. An allowance in the form of a specific number of worker hours and the cost of materials should be established by the general contractor.”


“The framing subcontractors can then compute the appropriate value of the allowance to include in their bids. For best cost control the framing subcontractor’s bid should stipulate the number of hours allocated for the repair work, not a fixed dollar value. It should be recognized that subcontractors tend to use different labor rates when bidding a project than they do when submitting change order requests.” 


  


  “Additionally, by including the labor and material value of this allowance in the framing subcontractors’ base bid, the subcontractor will already have the taxes, insurance, overhead, profit, and other markups on this work included in the bottom line of their base bid estimate. Therefore, the time and material charged to this allowance will be done so without any additional markups. Though repairing trade damage is an indirect cost of a project it is still an actual and necessary cost on a project and as such should be viewed as a standard base bid responsibility just as with the direct work.”


“Dents and dings to installed doors and frames are inevitable on a project. A plan should be in place for protecting doors and frames, as well as for making minor repairs. It is preferred that the protection be installed by the door subcontractor, with the maintenance and removal of the protection performed by the general contractor. Since the door subcontractor will not have a presence on the project after completing the door installation, it is not considered appropriate to hold them responsible for maintaining the protection or for damage caused by others.”


“Though this example is specific to the door trade, similar concerns exist with other installed items that might be damaged by different trades. If subcontractors are asked to protect their own work, it is important to also address the, often costly, maintenance and removal of this protection. Be sure to also address the inevitable minor repairs necessary due to trade damage throughout the trades, particularly the trades providing the building finishes.”


The authors suggest trade damage is inevitable and unavoidable. There was a time, in another industry, i.e., automotive, that oil leaking from the engine was accepted an inevitable result of the materials and assembly methods that went into producing internal combustion engines. Thank goodness the industry was unwilling to accept that paradigm!


The construction industry, like the automotive industry, also does not have to accept “inevitable” paradigms. Trade damage does not have to be accepted and a combination of materials/design, methods, and manpower can all contribute to reducing and eliminating trade damage.


If eliminating trade damage around doors and frames is your area of interest, make sure to review the benefits of the Qwikinstall Two-piece Interlocking Welded Hollow Metal frame. It is designed to be installed after most trades have left the construction site so, by design and method, trade damage is greatly reduced or avoided.    

By Scott Behr 09 May, 2022
 Supply chain lead times for welded hollow metal doors, frames, and hardware have gone from weeks to months in the last two years. It is not unusual to hear about lead times for welded hollow metal frames running as long as six months. Most projects simply cannot tolerate those kinds of lead times. There are reasons for the long lead times. The pandemic is generally accepted as the start of the many supply chain issues companies face today. The shuttering of businesses to reduce the spread of Covid coupled with the length of the pandemic cause supply change shortages and extended lead times across all commodities. Additionally the pandemic highlighted the significant dependence the US economy has on imported goods, steel in particular. As steel production moved overseas, production capacity in the US fell off. When the effects of the pandemic began to loosen in the US, steel continued in short supply because US production capacity could not make up for the import shortages (that continued in other countries due to their Covid issues). In the near-term shortages of steel will continue. Analysts predict an easing of steel supply issues in 2022 but Covid continues to throw the predictions out the proverbial window. While there are projects underway to add steel production capacity in the US, shortage issues, and the related higher prices of steel, will continue to frustrate the markets. One way to alleviate the impact of long lead times is to order the doors, frames, and hardware later in the project. In theory that would allow other portions of the project to proceed in spite of the lack of the ready availability of welded frames. Sounds simple enough except welded frames are installed early in the project, i.e., when the walls are being framed. The alternative is to use knock down frames which are installed after the walls are completed. Knock down frames have been available as long as welded frames. The compromise however is they do not provide the same structural strength or longevity of the welded frames. Customers overwhelmingly prefer welded frames. There is another alternative. The Qwikinstall frame system is a two-piece interlocking welded hollow metal frame that installs after the walls are complete. It installs with 1 person, in 6 steps, in 6 minutes. No other welded frame installs faster than Qwikinstall and no other frame combines the strength and durability of welded frame with the benefits of installation after the walls are complete. If welded hollow metal frames are negatively impacting your project timeline, do yourself a favor and look into the Qwikinstall welded hollow metal frame solution.
By Scott Behr 12 Apr, 2022
To Shim Or Not To Shim, Is That Really The Question?
Two Skilled Labor Construction workers discussing a project
By websitebuilder 05 Apr, 2022
Construction Labor Shortage
By websitebuilder 22 Mar, 2022
A quick look at everything you need to know about metal door frames.
Share by: